Patient Bed Tower Update

Patient Bed Tower Update

The 100,000-square-foot Patient Bed Tower and parking structure are near completion. Workers are waiting to install the tempered glass. The parking structure has been power washed, and the floors will be striped with paint. The flooring on the Patient Bed Tower’s second floor is complete. Flooring is being installed on the third and fourth floors. The built-in cabinets are complete. The soundscapes (colored ribbon artwork hanging from the ceiling) are now installed in the lobby and near the conference rooms on the first floor. The concrete in front of the drive is being poured this week. The drive will include speed bumps for extra safety. The project is on time with the Outpatient Clinic staff expecting to move to the second floor of the Patient Bed Tower around Labor Day.